US Steel today announced the restart of construction on an advanced electric arc furnace (EAF) steelmaking facility at its Tubular Operations in Fairfield, Alabama. US Steel previously initiated construction of the EAF in March 2015 and suspended construction in December 2015 due to unfavorable market conditions. 

The investment to complete the EAF, which includes modernization of the existing rounds caster, is expected to be approximately $215 million and add about 150 full-time employees. The EAF will have an annual capacity of 1.6 million tons. Construction is expected to begin immediately and the furnace is expected to produce steel rounds in the second half of 2020.

“We are pleased to announce the achievement of the market and performance stage gates required to restart our Tubular Segment EAF. We are committed to investing in the sustainable steel technology required to be a value-added tubular solutions provider for our customers,” said President and Chief Executive Officer David B. Burritt in a press release.


Similar articles

US structural pipe and tube exports up 9.9 percent in February

22 Apr | Steel News

US structural pipe and tube imports down 6.5 percent in February

19 Apr | Steel News

US structural pipe and tube exports down 41.7 percent in January

22 Mar | Steel News

US structural pipe and tube imports up 13.6 percent in January

19 Mar | Steel News

US rig count increases while Canadian count drops week-on-week

23 Feb | Steel News

US structural pipe and tube exports down 22.3 percent in December

23 Feb | Steel News

US structural pipe and tube imports up 9.9 percent in December

16 Feb | Steel News

US OCTG imports up 51.8 percent in December

07 Feb | Steel News

US rig count drops while Canadian count rises week-on-week

02 Feb | Steel News

US and Canadian rig counts increase week-on-week

26 Jan | Steel News