Severstal completes major overhaul at Cherepovets converter steel production facility

Friday, 15 May 2026 11:33:48 (GMT+3)   |   Istanbul

Russian steelmaker Severstal has announced that it has completed a major overhaul program at its converter steel production facility at the Cherepovets Iron and Steel Works (CherMK), the company’s key asset.

The works, completed in line with the equipment shutdown schedule, covered converter No. 3, ladle furnace No. 1, the steel vacuum unit, and continuous steel casting units No. 2 and No. 5. Severstal stated that the program is aimed at reducing downtime, improving production efficiency and ensuring equipment reliability.

The total cost of the overhaul amounted to RUB843 million ($11.5 million). According to the company, the project will also support better working conditions, product quality and compliance with environmental standards.

Severstal added that its own divisions and key contractors from the Vologda Region, where CherMK is located, were involved in the repair works.


Similar articles

Severstal decommissions rolling mill 150 at CherMK steel plant

03 Jun | Steel News

Severstal enhances energy efficiency with furnace modernization at CherMK

29 May | Steel News

Russia’s Severstal reports weaker Q1 2026 results amid lower steel prices, weak Russian demand

22 Apr | Steel News

Severstal revises 2026 budget amid weakening steel demand

30 Mar | Steel News

Severstal starts cold commissioning of pelletizing plant at CherMK

26 Mar | Steel News

Russia’s Severstal completes overhaul of galvanizing line at Cherepovets plant

11 Mar | Steel News

Severstal outlines $1.27 billion investment program for 2026 in CherMK, focuses on low-carbon production

10 Feb | Steel News

Severstal posts 78.6% lower net profit for 2025, pressure on demand to persist in 2026

03 Feb | Steel News

Russia’s Severstal completes major seasonal blast furnace repairs at CherMK

27 Nov | Steel News

Russia’s Severstal completes major converter overhaul at CherMK

19 Nov | Steel News