Severstal completes $1.8 million overhaul of electric steelmaking facilities at Cherepovets plant

Tuesday, 17 November 2026 13:58:05 (GMT+3)   |   Istanbul

Russian steelmaker Severstal has completed a major overhaul of electric steelmaking facilities at its Cherepovets Iron and Steel Works (CherMK), focusing on improving equipment reliability, operational efficiency and environmental performance.

The RUB 143 million ($1.8 million) repair campaign covered electric arc furnace No. 1 (EAF-1) and ladle furnace No. 2 (LF-2), including the replacement of a vertical water-cooled flue gas duct, upgrades to the slag corridor and repairs to electrical and power equipment.

With an annual production capacity of 1.3 million mt, EAF-1 can operate using different raw material combinations, including a charge consisting of 85 percent hot metal and 15 percent scrap, providing greater flexibility in steel production.

According to Evgeny Vinogradov, CEO of Severstal's Russian Steel and Resource Assets Division, the new flue gas duct will improve furnace reliability, reduce dust accumulation and minimize the risk of damage to gas cleaning equipment.

BoraKadıoğlu
Bora Kadıoğlu
Editor
All Articles by the Author

I graduated from Boğaziçi University with a degree in Translation and Interpreting Studies. I have been working in the iron and steel sector for three years as a content specialist at SteelOrbis, mainly focusing on plant investments, steelmaking technology, and import/export statistics.

Similar articles

Severstal starts equipment installation at 149 MW CherMK power plant

Severstal targets 2026 launch for Cherepovets pellet plant

Severstal's Q3 2026 net profit rises 17 percent despite lower steel sales

Severstal rolls first coil on third production line of wire rod mill 170

Severstal expands Forcera weathering steel range with thin sheet products

Severstal completes $15.3 million converter overhaul at CherMK

Severstal develops digital installation technology for CherMK galvanizing line upgrade

Severstal’s net profit plunges 74 percent in Q2 2026 amid lower steel prices

Severstal starts commissioning of $1.48 billion iron ore pellet plant

Severstal’s CherMK lowers solid fuel use at blast furnace No. 4 to record level