CSN halts operation of blast furnace in Brazil

Wednesday, 22 January 2025 02:14:03 (GMT+3)   |   Sao Paulo

The Brazilian steel and iron ore producer, CSN, started a prescheduled stoppage for maintenance and revamping of its blast furnace number two (BF-02) at the Volta Redonda plant, located in the state of Rio de Janeiro.

The works are expected to conclude in 2025, at a cost estimated at $260 million, increasing the useful life of the equipment by eight years.

With the temporary stoppage of BF-02, which has a pig iron production capacity of 1.5 million mt per year, it is expected the company will increase its acquisitions of slabs to feed its rolling operations from Ternium or from ArcelorMittal Pecem, its domestic alternatives, or from imports.

The Volta Redonda plant has a pig iron production capacity of 5.08 million mt per year.


Similar articles

Brazilian crude steel production declined in October

20 Nov | Steel News

Brazil’s CBMM plans increase of niobium production ahead of demand

31 Oct | Steel News

Samarco achieves record production in Q3

29 Oct | Steel News

Vale production increased for Q3 2025

22 Oct | Steel News

Brazilian automotive production declines in September

08 Oct | Steel News

Brazilian crude steel production declines 4.6 percent in August 2025

18 Sep | Steel News

ArcelorMittal is concluding the expansion of iron ore mine in Brazil

15 Aug | Steel News

Samarco releases operational report for the second quarter of 2025

25 Jul | Steel News

Vale production increased in the second quarter of 2025

23 Jul | Steel News

Brazilian crude steel production declined in June

18 Jul | Steel News