NLMK commences test production at new reheating furnace

Thursday, 03 October 2019 11:28:57 (GMT+3)   |   Istanbul

Russian steelmaker NLMK announced that its flagship site NLMK Lipetsk has started test production at its new reheating furnace at Mill 2000. With the installation of this new reheating furnace, NLMK Lipetsk’s hot rolled steel capacity will increase by two percent or 110,000 mt and this furnace will reduce energy consumption and air emissions by 50 percent.

This new reheating furnace will boost furnace productivity by 23 percent to 2.25 million mt per year. Total investments in the project amounted RUB 4.3 billion ($66.06 million) and ramp-up to full capacity is expected before the end of 2019.

 “The construction of the new furnace is a key Strategy 2022 project. It will debottleneck our hot-strip operations and bolster our output of high quality HRC. With the new unit up and running, all of our steel for hot rolling will go through processing in new generation high performance resource-saving furnaces,” said Konstantin Lagutin, NLMK Group vice president for investment projects.

Similar articles

Russia’s NLMK reports lower net profit and sales revenues for 2025

Russia’s NLMK reports lower net profit and sales revenues for H1 2025

NLMK tests recycled wood technology to cut emissions

NLMK commissions gas cleaning unit at Novolipetsk

Russia’s NLMK posts lower steel production for H1

NLMK Lipetsk’s steel shipments by rail up three percent in February

NLMK likely to see limited impact from drone attack at coke plant

NLMK finally sells its longs business to IMH, ex-Russia pig iron shipments may be affected

Russia’s NLMK Lipetsk to recycle refractories as raw material

Russia’s NLMK launches new antibacterial coated steel