NLMK commissions gas cleaning unit at Novolipetsk

Tuesday, 28 January 2025 14:10:40 (GMT+3)   |   Istanbul

Russian steelmaker NLMK Group has announced that it has completed the installation of a gas cleaning unit on its newly commissioned ladle furnace at its Novolipetsk Iron and Steel Works.

Accordingly, the equipment will capture 99.9 percent of the dust emitted by the ladle furnace. As a result, the residual dust in the air following the cleaning will not exceed 5 mg per cubic meter.

Being Russia’s largest steelmaker, NLMK has a steel production capacity of 14.3 million mt per year.


Similar articles

Investment in Canadian building construction increases 2.3 percent in April 2026

26 Jun | Steel News

US and Canada rig count increases - week 26, 2026

26 Jun | Steel News

US flat steel prices advance even as global energy continues down amid shaky Iran deal

26 Jun | Flats and Slab

Mexico’s domestic ferrous scrap prices fall for third consecutive week

26 Jun | Scrap & Raw Materials

US import long steel prices decline amid cheaper Asian supply, reduced energy costs

26 Jun | Longs and Billet

Brazilian pig iron group Sindifer confirms law firm hire to support US tariff hearings

26 Jun | Steel News

Global View on Scrap: Price in Turkey falls to $375/mt CFR on lower end, Asia softens again as steel demand fails to ...

26 Jun | Scrap & Raw Materials

Local Turkish scrap prices decline as expected

26 Jun | Scrap & Raw Materials

HRC trade at standstill in EU as country-specific quota announcement awaited

26 Jun | Flats and Slab

Canadian iron ore production down 1.5 percent in April

26 Jun | Steel News