MMZ resumes production after delay due to gas dispute

Wednesday, 21 January 2009 15:27:29 (GMT+3)   |  

Moldavian Metallurgical Plant (MMZ) has stated that the recommissioning of its electric arc furnace (EAF) was delayed by three days, as, due to the Russian-Ukrainian gas dispute, MMZ's power supplier Moldova GRES reduced its electricity supplies. Even though gas deliveries to the plant were not cut completely, MMZ was forced to work in conditions of reduced gas consumption.

Accordingly, MMZ restarted operations at its EAF on January 15, 2009. Currently the plant's steelmaking facilities are working on a regime of maximum power load in the morning and afternoon, while in the middle of the day it operates only its rolling mill shop.

However, MMZ says that in 2009 it will continue to work according to plan, and is filling all received orders, regardless of the crisis and gas dispute.

During the first 19 days of 2009, MMZ produced 4,878 mt of crude steel and 22,202 mt of rolled steel products. On January 19, MMZ's deliveries amounted to 22,814 mt of steel products.

Similar articles

MMZ’s rolled steel output down 58 percent in July from June

MMZ’s rolled steel output up 80.1 percent in May from April

Moldova’s steel product consumption to reach 210,000-220,000 mt in 2010

Tangshan Yinghai Metal Materials' steel sheet project begins trial production

CPCA: Passenger vehicle sales in China estimated at 1.648 million units in October 2026

MOC: Average steel prices in China fluctuate in limited range in Nov 9-15

Regional integration, actionable trading plans, and the auto industry: ALACERO second day of conferences

Mexican domestic ferrous scrap prices continue to rise due to a rise in scrap exports

Alacero Summit 2026 highlights need for coordinated action against global steel overcapacity

Brazil renews steel import quotas at same volumes as recently expired round