Brazilian miner Vale said this week it plans to spend an additional $716 million to decommission several iron ore waste dams.
Vale said a new government rule has changed the status of its Doutor and Campo Grande dams to “upstream,” which means the miner will have to include them in their decommissioning plan.
The company said it will also spend another $87 million to other undisclosed “provision adjustments,” which will be reflected in its upcoming Q4 results, to be published on February 20, 2020.
Vale noted its plan for decommissioning dams following the Brumadinho disaster will continue for the next four years. The company already decommissioned its 8B dam in December 2019, and the Fernandinho dam should be decommissioned in 2020.