Salzgitter to supply 70,000 mt of steel for Meerwind Offshore Wind Park

Wednesday, 07 September 2011 17:23:32 (GMT+3)   |  
       

Ilsenburger Grobblech GmbH (ILG), a subsidiary of the Germany-based steelmaker Salzgitter Group, has won the contract from AMBAU GmbH for the delivery of around 70,000 mt of heavy plate for the Meerwind Offshore Wind Park to be located 50 km off the German coast in the North Sea.

As from October, ILG will be delivering 1,700 mt of plate per week and the plate to be supplied by ILG will be used for the foundation structures of the Meerwind Süd and Meerwind Ost offshore wind parks. The foundation structures will be manufactured in all five AMBAU plants from November 1, 2011 onwards.

The start of construction has been scheduled for the end of 2012 and commissioning will take place at the end of 2013.


Similar articles

US cut-length plate imports down 6.2 percent in February

23 Apr | Steel News

Japanese crude steel output up 2.9 percent in March from February

23 Apr | Steel News

Ex-China steel plate prices move sideways, local prices expected to rise

22 Apr | Flats and Slab

Romanian mill cuts local HRC prices sharply amid challenging trade

19 Apr | Flats and Slab

Consumption of steel plate in Mexico decreases 5.5 percent in February

18 Apr | Steel News

US plate prices mostly steady on adequate supply

18 Apr | Flats and Slab

Flat steel prices in local Taiwanese market - week 16, 2024

18 Apr | Flats and Slab

Japan’s HRP and HRS shipments up 8.9 percent in February from January

17 Apr | Steel News

US plates in coil exports up 14.6 percent in February

16 Apr | Steel News

Stocks of main finished steel products in China down 4.8% in early April

16 Apr | Steel News