Venezuela's Ferrominera advances construction of second pellet line

Thursday, 12 July 2018 00:26:54 (GMT+3)   |   Sao Paulo

Venezuelan state-owned iron ore producer CVG Ferrominera Orinoco (FMO) said this week its second pellet line is now 61 percent complete.

About 2,514 workers have been working in the project, which is expected to help the local iron ore producer to increase pellet supply in the domestic market. Ferrominera has a 25 million mt/year iron ore capacity, a 3.3 million mt/year pellet capacity, and a 1 million mt/year HBI capacity.

In March this year, works at the second pellet line was 53.09 percent complete. Ferrominera said in mid-June it was working to resume operations at its HBI plant. It said it replaced 22 catalyst tubes. The replaced equipment should last about five years.


Similar articles

Venezuela’s Sidor maintains iron ore pellet production

11 Jan | Steel News

Venezuelan state-run companies post marginal production figures in 2019

06 Jan | Steel News

Venezuela eyes pellet, iron ore and HBI exports by 2020

25 Jul | Steel News

Venezuela’s Sidor inaugurates second pellet line

21 Jun | Steel News

Venezuelan iron ore and steelmaking companies face protests, shutdowns

24 Oct | Steel News

Venezuela’s Ferrominera recovers damaged iron ore railroad

04 Oct | Steel News

Ferrominera sees recovery in iron ore production

05 Apr | Steel News

Venezuela’s Ferrominera expects to increase domestic supply of pellets

05 Mar | Steel News

Strike halts production at Venezuela’s Ferrominera

19 Jan | Steel News

Ferrominera Orinoco expected to produce less iron ore year-on-year

14 Dec | Steel News

Marketplace Offers

DRI
Dimensions:  9 - 16 mm
SUEZ STEEL CO.
HBI
Dimensions:  110 mm
ZISCO TRADING
Lumps
Dimensions:  0 mm
Iron Ore: %62
ZISCO TRADING