BMZ reconstructs railway terminal

Thursday, 25 December 2008 13:34:23 (GMT+3)   |  
       

Belarusian Iron and Steel Works (BMZ) has completed the reconstruction of its railway terminal Zavodskaya, which is used by the company for receiving raw material stocks and delivering its finished steel products.

As a result of 11 months reconstruction, which included the construction of an additional 6.5 km of railway, the building of 26 track switches, of a new compressor station, and of a new receiving yard fitted with modern equipment, BMZ increased the terminal's capacity by 40 percent. The cost of the project amounted to BY Ruble 28 billion (approx. $12.75 million).

The increase of railway terminal's capacity is in line with BMZ's plans to up its output capacity to three million mt per year. Over the last five years, BMZ has enhanced its annual output by 25 percent from 1.6 million mt to two million mt of steel products.


Similar articles

EUROFER: Recession in EU construction to continue in 2024

14 Feb | Steel News

EUROFER: EU construction to see bigger recession in 2023 than expected

03 Nov | Steel News

EUROFER: EU construction output rises by 4.8% in 2022, exceeding estimate

05 May | Steel News

Euro area construction output up 3.9 percent in Jan from Dec

22 Mar | Steel News

Euro area construction output down 2.5 percent in Dec from Nov

27 Feb | Steel News

Euro area construction output down 0.8 percent in Nov from Oct

23 Jan | Steel News

Euro area construction output up 0.1 percent in September from August

24 Nov | Steel News

EUROFER: EU construction activity to rise by 5.6% in 2022, to drop in 2023

31 Oct | Steel News

Euro area construction output down 0.6 percent in August from July

21 Oct | Steel News

Euro area construction output up 0.3 percent in July from June

20 Sep | Steel News