ArcelorMittal Spain shuts Avilés pickling line as part of €18 million upgrade

Tuesday, 09 December 2025 13:46:11 (GMT+3)   |   Istanbul

ArcelorMittal Spain has shut down the pickling line at its Avilés plant as part of an €18 million modernization program, according to media reports. The stoppage comes amid broader operational challenges across the company’s Asturias facilities, including ongoing issues restarting blast furnace “B” in Gijón and planned maintenance work on sinter plant “A”.

The Avilés pickling line, which removes oxide scale from hot rolled steel using diluted hydrochloric acid, will remain offline for three weeks. The €18 million upgrade includes replacing the hydrochloric acid storage tanks that feed the process, which treats coils coming out of the hot strip mill.

Ongoing failure of blast furnace “B” causing serious disruption

This modernization forms part of a broader €168 million investment package announced earlier this year for ArcelorMittal’s facilities in Avilés, Gijón, Sagunto, Etxabarri and Lesaka. A significant share of the total investment is earmarked for the hybrid electric arc furnace project in Gijón, while the Avilés pickling line revamp represents a key component of ongoing downstream improvements.

The shutdown will have immediate downstream effects, as the pickling line supplies strip to the tandem mill, temper mill and tinplate lines in Avilés.

ArcelorMittal has been unable to restart blast furnace “B” in Gijón for two months, following a maintenance shutdown during which the unit suffered several fires. Three attempts to restart the furnace using the oxy-lance method, injecting oxygen and propane, have failed due to a large mass of solidified iron inside the vessel.

As a result, the plant is facing an acute shortage of hot metal. With only blast furnace “A” operational, production levels are insufficient to supply all rolling and steelmaking units.

Hot metal shortages force prioritization and interruptions

Due to limited hot metal availability, ArcelorMittal is prioritizing hot strip production for the automotive sector, to avoid penalties, and rail manufacturing, which currently has strong order volumes.

Other downstream facilities are experiencing intermittent stoppages. The company informed employees that the shutdown of the Gijón heavy plate mill would be extended due to a lack of slabs available for rolling.

The Gijón plate mill sources its slabs from the Avilés melt shop, which is currently running at 60 percent of capacity because of the shortage of hot metal. Most of its limited output is being directed to the Avilés hot strip mill.


Similar articles

ArcelorMittal to build steel-powder production plant in Spain

06 Nov | Steel News

Spain approves €600 million in subsidies to offset carbon costs for electro-intensive industries

14 Oct | Steel News

ArcelorMittal Sestao picks Danieli for new green steel upgrades in Spain

25 Sep | Steel News

ArcelorMittal to strengthen distribution network in Spain with new center

13 Jun | Steel News

Spain’s ArcelorMittal Sestao to upgrade its strip mill

14 Mar | Steel News

ArcelorMittal Spain resumes wire rod and rail production in Gijón despite low demand

08 Jan | Steel News

ArcelorMittal Spain suspends wire rod and rail production at Gijón due to low demand

13 Dec | Steel News

ArcelorMittal Spain temporarily idles Gijón steelworks and wire rod plant

22 Oct | Steel News

ArcelorMittal Spain suspends coke battery due to explosion, output unlikely to be affected

19 Sep | Steel News

ArcelorMittal Spain invests €152 million in 2023 to increase competitiveness

29 Jul | Steel News