Vallourec to resume full production at Pau Branco iron ore mine in Brazil

Thursday, 11 May 2023 12:16:25 (GMT+3)   |   Istanbul

France-based pipe manufacturer Vallourec has announced that it has obtained the necessary permissions for full production resumption at the Pau Branco iron ore mine in Brazil by the end of the second quarter at the latest.

The mine’s operations were temporarily suspended in January last year following flooding-related damage and were partially restarted in May last year.

According to the statement, the company sold four million mt of iron ore from the mine in 2022, well below the full potential of an annual 8.7 million mt. In the first quarter this year, the company sold approximately 1.5 million mt of iron ore from the given mine, in line with the guidance.


Similar articles

Daily iron ore prices CFR China - May 29, 2026

29 May | Scrap & Raw Materials

Iron ore in China edges down further due to a slowdown in steel demand

28 May | Scrap & Raw Materials

Major steel and raw material futures prices in China - May 28, 2026

28 May | Longs and Billet

Daily iron ore prices CFR China - May 27, 2026

27 May | Scrap & Raw Materials

Major steel and raw material futures prices in China - May 27, 2026 

27 May | Longs and Billet

Daily iron ore prices CFR China - May 26, 2026

26 May | Scrap & Raw Materials

BHP scraps Pilbara iron ore decarbonization project amid rising costs and weak economics

26 May | Steel News

Major steel and raw material futures prices in China - May 26, 2026 

26 May | Longs and Billet

Brazilian high-grade iron ore price declines on high weekly transoceanic shipments

25 May | Scrap & Raw Materials

Daily iron ore prices CFR China - May 25, 2026

25 May | Scrap & Raw Materials

Marketplace Offers

DRI
Dimensions:  9 - 16 mm
SUEZ STEEL CO.
Lumps
Dimensions:  0 mm
ATAY COMPANY
Lumps
Dimensions:  0 mm
Wuchan zhongda international group