Severstal inks contracts with plantmakers to build new BF at Cherepovets

Thursday, 01 March 2018 13:41:41 (GMT+3)   |   Istanbul
       

Russian steelmaker Severstal has announced that it has signed contracts with Netherlands-based Danieli Corus BV, a subsidiary of the Italian plantmaker Danieli, Luxembourg-based plantmaker Paul Wurth and German-based engineering company TMT GmbH, for the construction of the new blast furnace (BF) No. 3 at its Cherepovets Iron and Steel Works.

The new blast furnace will have a design capacity of 2.9 million mt of pig iron per year and the total cost of the investment project is more than RUB 28 billion ($494.8 million). First equipment shipments are planned for the first quarter of 2019.


Similar articles

Severstal to establish JV to produce steel towers for wind power plants

13 Sep | Steel News

Paul Wurth inks contract with Severstal for new coke-making complex

30 Jul | Steel News

Primetals to modernize Severstal’s hot strip mill 2000 at Cherepovets mill

22 May | Steel News

Danieli to supply new continuous pickling line for Severstal

23 Mar | Steel News

Severstal completes reconstruction of BF No. 5 at Cherepovets mill

21 Dec | Steel News

Severstal uses new type of raw material

25 Dec | Steel News

Severstal starts building second ladle furnace at Cherepovets

12 Nov | Steel News

Severstal to invest RUB 2.5 billion in flat steel production in 2015

04 Jun | Steel News

Russian steel producers reach agreement with automakers

06 Mar | Steel News

Severstal completes Kaluga plant expansion project

20 Sep | Steel News