Bolivia’s El Mutun steel and iron ore complex project now 46 percent complete

Wednesday, 08 December 2021 21:31:03 (GMT+3)   |   Sao Paulo
       

The Bolivian El Mutun steel and iron ore complex project is now 46 percent complete, according to Bolivian officials. The Bolivian government, which owns Empresa Siderurgica del Mutun (ESM), so far invested about $546 million in the project.

The country’s minister of mining, Ramiro Guzmán, said the project should have a combined seven facilities, which include concentration, pelletizing, direct reduction, steelworks, rolling mill, power plant, and supporting areas.

The project is located in the city of Puerto Suarez in the province of Santa Cruz. Construction works were first expected to begin in 2017 but were then postponed for June 2018. Sinosteel commenced preliminary works in the area in July 2018. Earlier this year, the Bolivian government said construction works at the ESM complex could be completed by late 2022.


Similar articles

Daily iron ore prices CFR China - April 19, 2024

19 Apr | Scrap & Raw Materials

Vale's iron ore exports up 97.5 percent in January

19 Apr | Steel News

Major steel and raw material futures prices in China - April 19, 2024

19 Apr | Longs and Billet

Iron ore prices continue to rise, heading towards $120/mt CFR

18 Apr | Scrap & Raw Materials

India’s coking coal import traffic at ports up 10% in FY 2023-24

18 Apr | Steel News

BHP Billiton’s iron ore output down in Q3 FY 2023-24, metallurgical coal output forecast lowered

18 Apr | Steel News

China’s iron ore output increases by 15.3 percent in Q1

18 Apr | Steel News

Major steel and raw material futures prices in China - April 18, 2024

18 Apr | Longs and Billet

Brazilian high-grade iron ore price increases sharply week-on-week

17 Apr | Scrap & Raw Materials

Iron ore production increases at Vale in Q1

17 Apr | Steel News