According to preliminary data for January, Ilyich received just 43,300 metric tons of
scrap of the 60,000 metric tons initially projected, thus filling only 72.2 percent of the plant's
scrap requirements.
Supplies of
scrap to
Zaporizhstal in January 2007 were by 29.5 percent less than the plant's projected monthly needs of 80,000 metric tons, totaling 67,600 metric tons.
Enakievsk MZ during the same period received 45,900 metric tons of
scrap - showing a 19.5 percent shortage compared to its expected requirements.
Mittal Steel Kriviy Rih obtained 24,100 metric tons of
scrap during the first month of 2007 -74 percent less than its planned
consumption of 93,000 metric tons.
Alchevsk received 49 percent less
scrap than its planned
consumption of 63,000 metric tons. The January supplies of
scrap to the mill totaled 37,200 metric tons.
Istil received 53,400 metric tons of
scrap in January 2007, below its projected requirements of 99,000 metric tons by 46.1 percent.
Azovstal received 72.7 percent less
scrap than its planned volume of deliveries for January 2007 – 60,000 metric tons. The
scrap supplies to the plant totaled 16,400 metric tons.
Scrap supplies to Ukrainian steel mills in Dec 2006