NLMK completes CCM-4 modernization

Friday, 11 April 2008 14:31:02 (GMT+3)   |  

The Russian steel producer Novolipetsk Steel (NLMK) has announced the completion of the modernization of the continuous casting machine (CCM-4) with an annual production capacity of two million metric tons located at its main production site in Lipetsk.

The modernization of the CCM-4 allows NLMK to increase the speed of slab treatment by 20-30 percent and also to maintain the high quality of produced products. The curvilinear two-strand machine can cast steel at a speed of up to 1.6 meter/min into concast slabs of 200-260 mm thickness, 800-1,850 mm width and 4,500-11,500 mm length.

NLMK invested Ruble 250 million in this project, which was implemented in cooperation with Siemens VAI.

Similar articles

NLMK Indiana’s Jan-Oct production at all-time high

NLMK posts slight fall in crude steel output for Q3

NLMK to maintain August output at July levels

NLMK to maintain May output at April levels

NLMK’s slab casting capacity improves after revamp

NLMK casts first slabs at the revamped continuous casting machine in Lipetsk

Russia’s NLMK to invest €100 million in rolling mill at DanSteel

NLMK produces new products

NLMK/Duferco JV’s 2010 sales rise 22 percent on back of stable demand

NLMK’s Lipetsk site’s steel sales increase by 11 percent in 2010