CEO denies rumors of technical failure at Bolivia’s El Mutun

Tuesday, 02 December 2025 07:31:43 (GMT+3)   |   Sao Paulo

The Bolivian El Mutun steel complex halted operations just two weeks after opening, sparking rumors of technical issues and local media claims that it is a white elephant.

Jorge Alvarado Rivas, Chief Executive Officer of the complex, announced that equipment testing was completed successfully and all facilities operated reliably without any malfunctions. 
 
Rivas stated that production was halted because of difficulties obtaining imported raw materials, a shortage of foreign currency, and issues acquiring diesel fuel. 
 
"The steel complex isn't stopped; it's awaiting inputs," he said. 
 
Regarding the requests for auditing procedures, Rivas stated that he is available to meet with the authorities to discuss the matter. 
 
El Mutun comprises seven facilities: iron ore concentration, pelletizing, DRI, steel manufacturing, rolling, an electric center, and support services. Its annual output capacity for rebars and wire rod reaches 200,000 metric tons.  

Similar articles

Tenova’s ENERGIRON plant achieves first DRI production at Bolivia

19 Nov | Steel News

El Mutun Steel Complex initiates steel production in Bolivia

13 Nov | Steel News

El Mutun Steel Complex initiates DRI plant operations in Bolivia

14 Oct | Steel News

Annual performance of the Chilean economy increased in March

16 May | Steel News

Billet production commences at Bolivia's El Mutún steel complex

01 Apr | Steel News

Rebar and wire rod production start at Bolivia’s El Mutún steel complex

14 Jan | Steel News

Equipment tests started at Bolivia’s El Mutún steel complex

05 Nov | Steel News

Bolivia’s El Mutun iron ore and steel complex will start operations in September

20 Aug | Steel News

Bolivia’s El Mutun project to start finished steel production in March 2025

27 May | Steel News

Bolivia’s El Mutun considering cooperation with Brazilian pig iron producer

08 May | Steel News