Baku Steel commissions new EAF

Tuesday, 05 August 2014 17:33:24 (GMT+3)   |   Istanbul

Austrian plantmaker Siemens Metals Technologies announced that the electric arc furnace (EAF) supplied by Siemens has been put into operation at Azerbaijani steel producer Baku Steel. The new furnace is part of an expansion project with which Baku Steel wishes to boost its annual production capacity to around 1.1 million mt of steel.

With the new 50-mt electric arc furnace from Siemens, the company can produce 500,000 mt of steel a year, some 150,000 mt more than with the previous plant.

The electric steel plant was equipped with an off-gas cleaning system as part of the project, so its dust emissions can be reduced to a maximum of 10 milligrams per standard cubic meter. Recently, Siemens also modernized the electric steel plant's ladle furnace and installed a dynamic compensation system.

Similar articles

Azerbaijan and Kazakhstan collaborate to build HBI plant

Baku Steel doubles Azerboru’s pipe output with major modernization phase

Baku Steel Company reduces use of scrap in steelmaking

Baku Steel orders news electric arc furnace from Siemens VAI

New rolling mill to be commissioned in February 2012 in West Azerbaijan

CVS successfully commissions Azerbaijan-based DHT’s new rolling mill

Azeri steelmaker DHT Metal JV to commission new melting shop and rolling mill

Evraz Group: Construction boom is the main engine of CIS steel industry

USEC scrap to docks price drops from last week are backtracked, market remains stable

Brazilian high-grade weekly iron ore prices fall amid rising supply