The Ukrainian steelmaker Zaporizhstal has announced that as of December 2008 it has stopped its blast furnace (BF) No. 4 for reconstruction.

The reconstruction in question will be carried out in two phases. The first phase, which includes the construction of a new base under the BF, is to be realized in 2009, while the second phase of reconstruction will be carried out in 2010-2012.

By the end of the current month, Zaporizhstal is to start the removal from the BF of the residual materials and refractories.

Zaporizhstal's BF No. 4 was constructed in 1948, and to date has produced a total of 46.332 million mt of pig iron.


Similar articles

German crude steel output increases by 6.0 percent in January-March

25 Apr | Steel News

Japanese crude steel output up 2.9 percent in March from February

23 Apr | Steel News

Ex-Russia BPI sellers fail to achieve higher prices, hike attempts continue

19 Apr | Scrap & Raw Materials

MMK’s crude steel output down 2.9 percent in Q1

19 Apr | Steel News

Brazilian BPI mills target higher export prices, impact of scrap eases as discussed at IIMA meeting

18 Apr | Scrap & Raw Materials

Ukraine’s ArcelorMittal Kryvyi Rih posts higher output for Q1, plans 50% utilization

17 Apr | Steel News

China’s crude steel output down 1.9% in Q1, steel prices start to rebound in April

16 Apr | Steel News

Turkey’s pig iron imports increase by 57 percent in January-February

16 Apr | Steel News

Ukraine’s pig iron output up 32.1 percent in Q1

10 Apr | Steel News

Ansteel’s crude steel output up 0.15 percent in 2023

09 Apr | Steel News