London Mining revises down its 2013 production guidance

Thursday, 12 December 2013 17:05:54 (GMT+3)   |   Istanbul

UK-based London Mining, a global diversified miner targeting the steel sector, has announced that it has revised down its production guidance for 2013 to 3.3 to 3.4 million wet mt from 3.6 to 3.9 million wet mt, due to a negative stockpile adjustment to fourth quarter production, slower-than-expected completion of the processing plant upgrades, and reduced production due to continued effects from the wet season.

As of November 30, production for 2013 had reached 3.1 million wt mt, with sales of 3.3 million wet mt. The effects of the wet season at the Marampa mine in Sierra Leone continued into the fourth quarter with lower mining rates causing full depletion of the run of mine stockpile. This significantly impacted the company's ability to feed the processing plant with the appropriate ore blend on a consistent basis.

Marketplace Offers

DRI

Dimensions 9 - 16 mm
 
Tedarikçi SUEZ STEEL CO.
View Offer

Lumps

Dimensions 0 mm
 
Tedarikçi ATAY COMPANY
View Offer

Lumps

Dimensions 0 mm
 
Tedarikçi Wuchan zhongda international group
View Offer

Similar articles

London Mining cuts production guidance due to Ebola outbreak

London Mining sees increased iron ore concentrate production in Q2

London Mining seeks strategic partner for Marampa project

London Mining to supply iron ore to Cargill for five years

London Mining’s net loss narrows down in 2013

London Mining sees significant increase in iron ore sales in Q4

London Mining’s iron ore concentrate output increases in Q3

London Mining to spend $40 million for Marampa capacity increase

London Mining sees narrowing of net loss in H1

London Mining sees higher output as new plant completed ahead of schedule