Ukraine’s Zaporizhstal stops BF No. 4 for reconstruction

Monday, 26 January 2009 16:14:42 (GMT+3)   |  

The Ukrainian steelmaker Zaporizhstal has announced that as of December 2008 it has stopped its blast furnace (BF) No. 4 for reconstruction.

The reconstruction in question will be carried out in two phases. The first phase, which includes the construction of a new base under the BF, is to be realized in 2009, while the second phase of reconstruction will be carried out in 2010-2012.

By the end of the current month, Zaporizhstal is to start the removal from the BF of the residual materials and refractories.

Zaporizhstal's BF No. 4 was constructed in 1948, and to date has produced a total of 46.332 million mt of pig iron.


Similar articles

Zaporizhstal to finish PCI plant construction in autumn 2009

11 Feb | Steel News

The Ukrainian scrap market in Jan-May 2008 - UAMB (Ukrainian Scrap Association) President V.A.Kulichenko and UAMB ...

25 Aug | Steel News

Zaporizhstal proceeds with construction of PCI plant

25 Jul | Steel News

Zaporizhstal orders equipment from Siemens-VAI

14 Apr | Steel News

Nucor CSP up for 21st week on domestic demand, low imports, energy strength

08 Jun | Flats and Slab

Local pig iron prices in China - week 24, 2026

08 Jun | Scrap & Raw Materials

Russian BPI exporters to hold prices firm despite very slow demand, lower scrap prices

05 Jun | Scrap & Raw Materials

New round of tariffs posts threats to Brazilian pig iron exports to the US

03 Jun | Steel News

Brazilian BPI suppliers keep targets stable at high levels amid some acceptance in US

02 Jun | Scrap & Raw Materials

Ukraine’s Zaporizhstal posts production decrease in Jan-May 2026

02 Jun | Steel News

Marketplace Offers

Steelmaking Pig Iron
Dimensions:  0 mm
ZISCO TRADING
Steelmaking Pig Iron
Dimensions:  0 mm
STAR GLOBAL LLC.