Severstal completes overhaul of sinter shop No. 3 at Cherepovets mill

Thursday, 29 June 2017 16:10:37 (GMT+3)   |   Istanbul
       

Russian steelmaker Severstal’s subsidiary Cherepovets Steel Mill has announced that it has completed the overhaul of sintering machine No. 10 at its sinter shop No. 3.

According to the company’s statement, following repairs and investments in technical reequipment, the output of the overhauled sinter shop No. 3 will increase by 190,000 mt per year. Meanwhile, the total cost of the technical reequipment amounted to more than RUB 400 million ($6.78 million), of which RUB 100 million was spent on equipment repairs.


Similar articles

Evraz moves assets offshore

04 Apr | Steel Matters

Evraz moves assets offshore

04 Apr | Steel Matters