The Russian steelmaker Severstal has announced the beginning of equipment supplies for the second polymer coating line at its Cherepovets Steel Plant.

The line is due to be completed by the end of 2009 and will have an annual production capacity of up to 200,000 metric tons of polymer coated products. With the new line in place, Severstal's annual production capacity for polymer coated products will reach 400,000 metric tons.

The total investment in the project amounts to Ruble 2.3 billion ($98 million). The products from the new line will be supplied for the needs of the Russian shipbuilding industry.

In addition, Severstal plans to complete reconstruction works at its HDG line at Cherepovets at approximately the same time as the construction of the second polymer coating line. This will allow Severstal to increase the volume of feedstock for its new polymer coating line.


Similar articles

Romanian flats prices stable ahead of Orthodox Easter holiday

03 May | Flats and Slab

Flat steel prices in local Taiwanese market - week 18, 2024

02 May | Flats and Slab

Romanian flats prices stable despite slower trade

26 Apr | Flats and Slab

Flat steel prices in local Taiwanese market - week 17, 2024

25 Apr | Flats and Slab

Flat steel prices in local Taiwanese market - week 16, 2024

18 Apr | Flats and Slab

Turkish flats prices generally stabilize after holiday

16 Apr | Flats and Slab

Flat steel prices in local Taiwanese market - week 15, 2024

11 Apr | Flats and Slab

Baosteel cuts local HRC prices by $14/mt for May

11 Apr | Flats and Slab

Turkey’s coated and CRC prices mainly down amid low demand

05 Apr | Flats and Slab

Flat steel prices in local Taiwanese market - week 14, 2024

04 Apr | Flats and Slab