Russian steelmaker NLMK Group has announced that it has started hot-testing the pulverized coal injection (PCI) unit at blast furnace (BF) No. 6 at its Lipetsk plant, one of the largest blast furnaces at the plant with a capacity of 3.1 million mt of pig iron per year. Meanwhile, the hot-testing of the PCI unit is due to begin at blast furnace No. 7, which has a capacity of 4.3 million mt per year.
 
Hot-testing is scheduled to end and startup to begin in the third quarter of the current year. Capital expenditure for the PCI project at the two blast furnaces will amount to over RUB 6.8 billion ($119.55 million).
 
The company’s vice president for investment projects, Konstantin Lagutin, stated that by the end of this year 90 percent of the Lipetsk plant’s blast furnace capacities will be covered by this resource-saving PCI technology. The new technology will enable a 30 percent decrease in the consumption of expensive coke in the blast furnace process and a 50 percent reduction in the consumption of natural gas.

Similar articles

NLMK Metalware to commission new wire galvanizing line

10 Feb | Steel News

NLMK Lipetsk to boost steel output by 1 million mt and expand sales portfolio

18 Jul | Steel News

SMS to supply new continuous slab caster for NLMK Group

17 May | Steel News

NLMK Group invests over RUB 5.7 billion in environmental initiatives in 2017

03 Apr | Steel News

NLMK Lipetsk raises share of in-house power generation to 59 percent

07 Feb | Steel News

NLMK Group to boost capacity of steelmaking shop 2 at Lipetsk by 19%

21 Dec | Steel News

NLMK Kaluga to reduce usage of refractories by 25 percent

22 Nov | Steel News

NLMK ramps up resource-saving PCI technology in BF shop No.2

06 Nov | Steel News

NLMK Group starts construction of new briquetting plant in Lipetsk

31 Aug | Steel News

NLMK covers 90% of blast furnace capacity with PCI system

12 Jul | Steel News