ChTPZ to finish new pipe workshop in mid-2010

Wednesday, 15 April 2009 16:24:33 (GMT+3)   |  

One of the largest Russian pipe producers, Chelyabinsk Tube Rolling Plant (ChTPZ), may finish the construction of the new pipe electric-welding workshop No. 3 for the production of large diameter pipes in the middle of 2010. The initial term for the commissioning of the workshop, end of 2009, has been put back due to the economic crisis, CHTPZ chairman Mr. Alexander Fyodorov stated.

The total investments in the workshop construction project amount to €500 million, of which €300 million has already been paid, while the remaining €200 million are expected to be secured in credit lines from Russian banks.

ChTPZ has already received more than 60 percent of the equipment, manufactured by the German plantmaker SMS Meer. The new pipe electric-welding workshop, with an annual capacity of 600,000 mt, will produce longitudinal welded pipes of 508 to 1,420 mm in diameter with multi-layer double-side polymer coating, with wall thicknesses of up to 48 mm, and of 18 m in length, for trunk oil and gas pipelines.

The new pipe electric-welding workshop No. 3 will be able to use up to 60 percent of MMK's plate mill 5000, which will be commissioned on July 19, 2009, and will have two production lines, one for manufacturing pipes of 18 m in length with wall thicknesses up to 38 mm, and the other for pipes of 12 m in length with wall thicknesses up to 48 mm.


Similar articles

Japanese crude steel output rises slightly in April 2026 year on year

22 May | Steel News

Japanese crude steel output down 4.1 percent in March 2026

22 Apr | Steel News

Most EU steel import quotas exhausted as Q1 ends, usage exceeds 90% in key segments

27 Mar | Steel News

Japanese crude steel output stable in February 2026

25 Mar | Steel News

Jingdong Steel’s $500 million Algerian steel plant reaches 60 percent completion

25 Feb | Steel News

Japanese crude steel output down 0.5 percent in January 2026

20 Feb | Steel News

Vietnam targets 75-80 million mt output by 2050 under new national steel strategy

12 Feb | Steel News

Japanese crude steel output down four percent in 2025

26 Jan | Steel News

Japanese crude steel output down 1.2 percent in November 2025

22 Dec | Steel News

Japanese crude steel output down one percent in October 2025

21 Nov | Steel News

Marketplace Offers

ERW Longitudinal Black Pipe
External Diamater:  21.3 - 323.9 mm
Wall Thickness:  2 - 12.5 mm
S195T / P235JRH
ARKON ÇELİK SAN. VE TİC. LTD. ŞTİ.
ERW Longitudinal Black Pipe
External Diamater:  21.3 - 323.9 mm
Wall Thickness:  2 - 12.5 mm
S195T / P235JRH
ARKON ÇELİK SAN. VE TİC. LTD. ŞTİ.
ERW Longitudinal OCTG Line Pipe
External Diamater:  21.3 - 323.9 mm
Wall Thickness:  2 - 12.5 mm
Gr B / X42
ARKON ÇELİK SAN. VE TİC. LTD. ŞTİ.