Ruukki completes steel-framed building for Outokumpu

Monday, 14 November 2011 13:55:08 (GMT+3)   |  
       

Finland-based steelmaker Ruukki has announced that it has built the new steel-framed industrial hall at Finland-based stainless steelmaker Outokumpu's steel plant in Tornio, northern Finland. The extension was built at a "logistically optimal location" between the existing hot rolling mill and steel melting shop without disrupting production.
 
According to Ruukki's statement, the construction started in early 2008, when Outokumpu decided to increase the special steel output at its Tornio steel plant. This capacity expansion required a new grinding machine and the new production facilities to house it.

Production at the plant did not stop during the construction process. Steel billets are ground in the grinding hall. The billet conveyor belt had to operate until the new roller table to convey the billets was completed.


Similar articles

Local Chinese stainless steel prices mostly increase

24 Apr | Flats and Slab

Ex-China stainless steel prices move up

23 Apr | Flats and Slab

China’s stainless steel exports up 9.8 percent in Q1

22 Apr | Steel News

Flat steel prices in local Taiwanese market - week 16, 2024

18 Apr | Flats and Slab

Local Chinese stainless steel prices mostly increase slightly

17 Apr | Flats and Slab

Ex-China stainless steel prices move sideways, demand rebounds

16 Apr | Flats and Slab

Global stainless steel output up 4.6 percent in 2023

16 Apr | Steel News

Flat steel prices in local Taiwanese market - week 15, 2024

11 Apr | Flats and Slab

Chinese stainless steel prices stable or slightly higher

10 Apr | Flats and Slab

Ex-China stainless steel prices edge up

09 Apr | Flats and Slab