Russia’s Ashinskiy Metallurgical Works to restart earlier OHFs

Monday, 26 January 2009 09:06:49 (GMT+3)   |  
       

Russian steel producer Ashinskiy Metallurgical Works (Ashinskiy) has decided to restart on January 28 operations at two of its three open hearth furnaces (OHF), which were stopped on December 22 for scheduled repair works and were planned to be recommissioned on February 1.
 
Accordingly, the OHF repair works are to be finished five days earlier, as Ashinskiy's flat rolling mill No. 1 has received additional orders for steel plates (orders for 28,500 mt as opposed to the predicted 10,000 mt), and also as the plant's current reserves of slabs are not sufficient.
 
In addition, Ashinskiy is to carry out a two-day urgent overhaul at its flat rolling mill No. 1, which will allow the plant to cut steel sheets of 12 m in width and 30 mm in thickness.
 
In 2008, Ashinskiy produced 652,321 mt of crude steel, exceeding its production plan for the year by 0.6 percent, and manufactured 480,224 mt of rolled steel products. The plant's total deliveries of steel plate amounted to 436,824 mt, including 317,821 mt supplied in the domestic market - up 4.5 percent year on year.

Similar articles

Romanian mill cuts local HRC prices sharply amid challenging trade

19 Apr | Flats and Slab

Consumption of steel plate in Mexico decreases 5.5 percent in February

18 Apr | Steel News

US plate prices mostly steady on adequate supply

18 Apr | Flats and Slab

Flat steel prices in local Taiwanese market - week 16, 2024

18 Apr | Flats and Slab

Japan’s HRP and HRS shipments up 8.9 percent in February from January

17 Apr | Steel News

US plates in coil exports up 14.6 percent in February

16 Apr | Steel News

Stocks of main finished steel products in China down 4.8% in early April

16 Apr | Steel News

Mexico maintains AD duties of 29.3 percent to plate imports from Russia

15 Apr | Steel News

Brazilian heavy plate exports and imports decline sharply in March

15 Apr | Steel News

Flat steel prices in local Taiwanese market - week 15, 2024

11 Apr | Flats and Slab