After delay, production finally begins at Nucor’s Louisiana DRI plant

Monday, 30 December 2013 01:06:13 (GMT+3)   |   San Diego
       

Nucor Corporation announced Friday the successful start-up of production at its direct reduced iron (DRI) facility in St. James Parish, Louisiana.  Production of DRI began on Tuesday, December 24, and has continued at planned ramp-up levels since that time.  The quality of material being produced in terms of both metallization and carbon content has improved very quickly, and within the first 24 hours of operation, output quality began matching the levels achieved at the company’s DRI plant that has been operating in Trinidad since 2006.

In late September, the collapse of an iron ore pellet storage dome on the plant site delayed its start-up, which was originally planned sometime in October.  The DRI plant is expected to produce 2.5 million tons of DRI per year.


Similar articles

Daily iron ore prices CFR China - April 19, 2024

19 Apr | Scrap & Raw Materials

Vale's iron ore exports up 97.5 percent in January

19 Apr | Steel News

Major steel and raw material futures prices in China - April 19, 2024

19 Apr | Longs and Billet

Iron ore prices continue to rise, heading towards $120/mt CFR

18 Apr | Scrap & Raw Materials

India’s coking coal import traffic at ports up 10% in FY 2023-24

18 Apr | Steel News

BHP Billiton’s iron ore output down in Q3 FY 2023-24, metallurgical coal output forecast lowered

18 Apr | Steel News

China’s iron ore output increases by 15.3 percent in Q1

18 Apr | Steel News

Major steel and raw material futures prices in China - April 18, 2024

18 Apr | Longs and Billet

Brazilian high-grade iron ore price increases sharply week-on-week

17 Apr | Scrap & Raw Materials

Iron ore production increases at Vale in Q1

17 Apr | Steel News